Solar Solutions

 

Capacity of solution, no of people served, problem faced by customer, benefits of solution to customer. The project was done in two phases. First phase was supply and Installation of 3,000Litres commercial solar hot water systems to two number blocks at the training centre. This was successfully commisioned in DEC 2017.

The second phase was installation of another 3000 litres commercial solar hot water systems for another 2No. Blocks at the Centre. This was done and completed in November 2018 The third phase of another 3,000Litres System will be done in 2019.

The centre serves KCB training staff HE CENTRE SERVES KCB TRAINING STAFF, WITH A BED CAPACITY OF 400, AND ALL ARE SERVED HOT WATER FOR SHOWERS BY THE SOLAR HOT WATER SYSTEM. The centrehas been able to reduce their power bill substantially by over 40% by installing the solar hot water systems.